Equipment Loading & Unloading at Difficult Sites
Not every site has a ground-floor bay with a wide corridor running straight to the room. Upper floors, tight lift shafts, narrow street access and constrained loading areas are the norm in Indian cities — and the equipment still has to get in.
When the standard route does not work
Corridor widths, door openings, lift dimensions, lift capacity and turning radii are measured against the actual equipment dimensions during site assessment. If any single one of them falls short, the conventional route is not viable — and that has to be known before the site is committed to, not discovered on delivery day with a crane booked and a gantry on a truck.
A magnet or gantry does not negotiate. If the turning radius at one corner is 200mm short, the route is closed, regardless of how good the rest of it is.
Craneage and skating
Where a building will not take the equipment through conventional routes, the alternatives are planned as part of site logistics:
- External craneage through a temporary structural opening — a planned, engineered opening in the facade or slab, formed and reinstated as part of the works
- Skating the load across prepared surfaces, with load spreading where the slab needs it
- Temporary structural openings internally, where a wall is the only obstacle
- Load path preparation along the route, since transit loads concentrate into small contact areas
Each of these needs coordinating with building management, local authorities, and traffic requirements where public roads or external space are involved.
Permissions are part of the plan
Craneage that occupies a public road or external space typically needs municipal or traffic permission, and that has a lead time. Building management in a shared or occupied building will have their own conditions — working hours, lift usage, protection of common areas. We scope and coordinate these as part of the logistics plan rather than discovering them the week before.
Plan it before you sign, not after
An equipment ingress and rigging study during feasibility establishes whether a site needs this kind of solution at all, and what it would cost. That turns a hidden risk into a line item you can compare across candidate sites.
Site access, answered.
How do you get an MRI magnet to an upper floor with no adequate lift?
Does craneage need separate approval from local authorities?
Can a temporary opening be made in a structural wall?
When should the ingress study happen?
What if the equipment has already been delivered to site?